How long does a sign permit take in Kansas City?
Typically 21 days. That is the median across 151 sign permits Kansas City has issued since 2025-01-01 — but one in ten took 98 days or longer.
That puts Kansas City 9 th fastest of the 15 cities measured. Seattle issues permits in the same day; Los Angeles takes 50 days.
Busiest sign contractors in Kansas City
By number of sign permits pulled since 2025-01-01.
- 1. REACHING SOLUTIONS LLC 32
- 2. Midwest Sign Company 21
- 3. SEE-MORE SIGNS MGF, INC. 11
- 4. Midtown Signs 11
- 5. KC Sign Express, Inc 10
- 6. Heartland Sign & Lighting 9
- 7. Young Sign Co., Inc. 8
- 8. Kansas City Sign Company, Inc. 8
- 9. INFINITY SIGNS, INC. 4
- 10. Staco Electric 4
Common questions
- How long does a sign permit take in Kansas City?
- A median of 21 days, measured across 151 sign permits issued since 2025-01-01. One in ten took 98 days or longer, so allow for that on a fixed deadline.
Where this comes from
Kansas City's own permit records, published as open data. We filter to sign permits using the city's permit-type values and measure the gap between the application and issue dates on each record. Medians rather than averages, because a few multi-year permits drag a mean somewhere useless.
Part of this wait belongs to the applicant. A permit can be approved and then sit unissued until its fees are paid, and the slowest records are typically ones where the city asked for revisions and got no reply — so read this as how long the whole process takes, not as how fast the office works.
This describes what the city did, not what it promises. A permit filed today may move faster or slower.
Source dataset · 154 records · computed 2026-08-02